TEST BANK FOR PMI (PMP) EXAM 6TH EDITION PMBOK (COMPLETE SOLUTION)

TEST BANK FOR PMI (PMP) EXAM 6TH EDITION
PMBOK (COMPLETE SOLUTION)
An element of the project scope statement is:
A. Acceptance criteria.
B. A stakeholder list.
C. A summary budget.
D. High-level risks. – A
Reserves Analysis – Risk management method of determining contingency or management reserves
for schedule
Which document describes the necessary information to determine if a project is worth the
required investment?
A. Cost baseline
B. Service level agreement
C. Memorandum of understanding
D. Business case – D
Which input to the Plan Risk Management process provides information on high-level risks?
A. Project charter
B. Enterprise environmental factors
C. Stakeholder register
D. Organizational process assets – A
Which item is an example of personnel assessment?
A. Resource calendar

B. Tight matrix
C. Team-building activity
D. Focus group – D
Which input to the Manage Stakeholder Engagement process provides guidance on how
stakeholders can best be involved in a project?
A. Feedback analysis
B. Stakeholder analysis
C. Communication management plan
D. Stakeholder management plan – D
Which input to the Identify Stakeholders process provides information about internal or external
parties related to the project?
A. Procurement documents
B. Communications plan
C. Project charter
D. Stakeholder register – C
The Identify Stakeholders process is found in which Process Group?
A. Initiating
B. Monitoring and Controlling
C. Planning
D. Executing – A
An input to Develop Project Charter is a/an:
A. Business case.

B. Activity list.
C. Project management plan.
D. Cost forecast. – A
Which Knowledge Area involves identifying the people, groups, or organizations that may be
impacted by or impact a project?
A. Project Risk Management
B. Project Human Resource Management
C. Project Scope Management
D. Project Stakeholder Management – D
Which input to Collect Requirements is used to identify stakeholders who can provide information
on requirements?
A. Stakeholder register
B. Scope management plan
C. Stakeholder management plan
D. Project charter – A
In which Knowledge Area is the project charter developed?
A. Project Cost Management
B. Project Scope Management
C. Project Time Management
D. Project Integration Management – D
The ability to influence cost is greatest during which stages of the project?
A. Early

B. Middle
C. Late
D. Completion – A
Which process involves developing an approximation of the monetary resources needed to
complete project activities?
A. Estimate Costs
B. Control Costs
C. Determine Budget
D. Plan Cost Management – A
Which tool or technique is used in the Develop Project Management Plan process?
A. Pareto diagram
B. Performance reporting
C. SWOT analysis
D. Expert judgment – D
The organization’s perceived balance between risk taking and risk avoidance is reflected in the risk:
A. Responses
B. Appetite
C. Tolerance
D. Attitude – A
An output of the Manage Stakeholder Engagement process is:
A. change requests
B. enterprise environmental factors
C. the stakeholder management plan

Leave a Comment

Scroll to Top